Notices · Solicitation
KAUTZ ROAD SUBSTATION CONSTRUCION, UIP SUBPROJECT 2- KRS
Open. Responses are due in 21 days, on December 18, 2026, 5:00 PM ET.
| Solicitation number | RFP-383167-CD |
|---|---|
| Notice type | Solicitation |
| Agency | ENERGY, DEPARTMENT OF, FERMILAB - DOE CONTRACTOR |
| Set-aside | None (full and open competition) |
| NAICS | 237130 Power and Communication Line and Related Structures Construction SBA size standard: $45M average annual receipts |
| Product or service code | Z2MZ Repair or Alteration of Epg Facilities - Other, Including Transmission |
| Place of performance | Batavia, IL 60510, USA |
| Posted | November 4, 2026 |
| Response due | December 18, 2026, 5:00 PM ET |
Who holds the work now
Largest current award in NAICS 237130 at the Department of Energy, by dollars obligated: EAST COAST POWERLINE LLC, current end date October 14, 2027. It may not be the contract this notice replaces.
Source: USAspending.gov, as of November 3, 2026.
Ask Claude about this notice
Add BidOpps AI to Claude, then type this:
Using BidOpps AI, read RFP-383167-CD in full and tell me what stage it's at.
Your first 10 searches are free. No card.
From the attachments
Pulled by AI from 8 of 18 files with text. Check the file before relying on a fact. A point with no row here was not found, which does not mean it doesn't apply. Each quote is the file's own words.
| Site visit | see the quote Exhibit C- Specification Set.pdf, page 9: "The General contractor and/or Trade sub-contractors are expected to make a site visit, create an existing building model based on LiDAR scan" |
|---|---|
| Bonding | 100 percent Performance Bond and 100 percent Payment Bond Exhibit H- Price Proposal Form.pdf, page 3: "Measurement and payment for this Bid Item shall include full compensation for the required 100 percent (100%) Performance Bond, 100 Percent (100%) Payment Bond" |
| Bonding | Payment and Performance Bonds Exhibit C- Specification Set.pdf, page 14: "2. Payment and Performance Bonds" |
| Past performance | EMR rates and OSHA 300 log for last three years Exhibit C- Specification Set.pdf, page 44: "Experience Modification Rating (EMR) Rates and Occupational Safety Health" |
| Past performance | Tree service firm with similar temporary tree and plant protection work Exhibit C- Specification Set.pdf, page 136: "Tree Service Firm Qualifications: An experienced tree service firm that has successfully completed temporary tree and plant protection work similar to that required for this Project" |
| Past performance | Facilitator with a record of successful learning performance in a similar training program Exhibit C- Specification Set.pdf, page 187: "in a training program similar in content and extent to that indicated for this Project, and whose work has resulted in training or education with a record of successful learning performance." |
| Contract type | firm-fixed-price Exhibit H- Price Proposal Form.pdf, page 1: "Please enter your total firm fixed price in words and numbers:" |
The notice text
The text below is SAM.gov's own, unedited.
Attachments
The files SAM.gov lists with this notice. Open them on SAM.gov, or ask Claude to read them.
- Exhibit H- Price Proposal Form.pdf
- Exhibit C- Specification Set.pdf
- Exhibit J- Proposal Cerftifications Form PUR-466_r5_10.14.25.pdf
- Exhibit N- Davis Bacon Wage Rater_ IL202600011.pdf
- Exhibit F - Statement of Acknowledgment (SF-1413).pdf
- Exhibit A- Scope of Work- UIP Subproject 2 KRS.pdf
- Exhibit K_Bond Bid FL-41.pdf
- Exhibit I- SARC_Subcontractor Annual RepsCerts.pdf
- Exhibit Q- Sample Firm-Fixed-Price Subcontract.pdf
- Exhibit P- Compliance With Federal Anti-Discrimination Laws- PRC EXH 469.pdf
- Exhibit O- Small Business Subcontracting Plan Template.pdf
- 383167 RFP 1.0 RFP Instructions to Offerors.pdf
- Exhibit L_FL-42 (Rev 1.25) - Payment Bond.pdf
- Amend 01 to RFP 383167-CD.pdf
- Exhibit G - Fermilab Subcontractor Safety Information Questionnaire.pdf
- Exhibit E - Construction Insurance Requirements.pdf
- Exhibit M_Performance Bond_FL-40.pdf
- Exhibit D- FFDG General Terms and Conditions for Construction (10.2026).pdf
- Exhibit B- Construction Drawing Set.pdf
What SAM.gov has posted, oldest first
| Notice | Posted | Response due |
|---|---|---|
| Solicitation | November 1, 2026 | December 18, 2026, 5:00 PM ET |
| Solicitation | November 4, 2026 | December 18, 2026, 5:00 PM ET |
Open solicitations like this one
Source: this notice on SAM.gov, from SAM.gov's public extract of contract notices, last loaded November 27, 2026.