Every answer cites notice numbers you can check on SAM.gov. See a real answer

Notices · Solicitation

USCG Cutter Eagle New Dredging for Berthing at New London City Pier

Closed. Responses were due October 22, 2026, 2:00 PM ET.

Solicitation number70Z0G126BSLISSW02
Notice typeSolicitation
AgencyHOMELAND SECURITY, DEPARTMENT OF, US COAST GUARD, CEU PROVIDENCE
Set-asideSmall Business Set Aside - Total (SBA)
NAICS23799
Product or service codeZ1KF Maintenance of Dredging Facilities
Place of performanceNew London, CT 06320, USA
PostedOctober 21, 2026
Response dueOctober 22, 2026, 2:00 PM ET

Who holds the work now

USAspending shows no current award in NAICS 23799 at the US Coast Guard, and this notice names no contract we hold.

Source: USAspending.gov, as of November 3, 2026.

Ask Claude about this notice

Add BidOpps AI to Claude, then type this:

Using BidOpps AI, read 70Z0G126BSLISSW02 in full and tell me what stage it's at.

Add to Claude

Your first 10 searches are free. No card.

The notice text

The text below is SAM.gov's own, unedited.

Posted ABSTRACT OF OFFERS IFB 70Z0G126BSLISSW02. AMENDMENT 0003 Posted October 16, 2026 to update Item 0002-Optional Item 1 in the IFB, by deleting the first paragraph to clarify that we're asking for the additional disposal costs for coated/treated piling. Please replace page 5 of the IFB with the updated one provided in this amendment. AMENDMENT 0002 Posted October 13, 2026 (Revised Bid Opening Date 10/22/2026 2pm EST) AMENDMENT 0001 Posted October 08, 2026 Eagle Pier New Dredging (FY26) at New London’s City Pier, CT (NEW LONDON COUNTY), PSN #24014900. Contractor shall provide all personnel, equipment, materials, and all other items and services required to perform dredging of a new area immediately south of CGC EAGLE’s berth at New London’s City Pier. The intent is to deepen the area to allow tugboats to assist the cutter for mooring/unmooring at all tide levels. Requirements of the design specify dredging to a depth of -17.0’ at Mean Lower Low Water (MLLW) +2.0’ over dredging allowance. This equates to approximately 3,700 cubic yards (CY) of dredge spoils to remove to an upland disposal site. Offshore disposal is not permitted due to environmental sample analysis of the dredge area. There is an environmental time of year restriction in Connecticut that only permits dredging activities between October 1st and March 1st. SPECIAL NOTES: The contractor shall conduct dredging operations so that navigation through the channel is possible at all times. The scope of work also includes removals of approximately 50 piles that remain below the waterline. Any piles that cannot be fully removed are to be cut at -21.0’ MLLW. Dredge quantity of 3,700 CY. This estimate is based on an average of the past annual dredging and surveys. The Contractor shall provide a cost for dredging per cubic yard. That per cubic yard cost will be used for any necessary contract cost adjustment resulting from dredging more or less than the estimated 3,700 cubic yards, within the limits of dredge. Contractor will be compensated for actual quantity of dredge material removed and disposed, within the limits of dredge, as shown on the plan sheets. Dredge disposal site location is to be determined by conditions of treated/non-treated piles for Base bid item and Option Bid item. The estimated value of the procurement is between $1,000,000 and $5,000,000. A 20% bid guarantee is required. Performance and Payment bonds will be required. The performance period is estimated to be 300 calendar days from issuance of Notice to Proceed. This acquisition is issued pursuant to FAR Part 14 Sealed Bidding and is 100% Set-Aside for Small Business concerns. All relevant solicitation documents, including specifications and drawings may be accessed for download beginning on the date of issue of the IFB at the following site: https://www.sam.gov. Vendors MUST be registered in the System for Award Management database through https://www.sam.gov in order to receive a federal government contract. THE GOVERNMENT RESERVES THE RIGHT TO CANCEL THIS SOLICITATION EITHER BEFORE OR AFTER THE CLOSING DATE. NO REIMBURSEMENT WILL BE MADE FOR ANY COSTS ASSOCIATED WITH PROVIDING INFORMATION IN RESPONSE TO THIS PRESOLICITATION NOTICE OR ANY FOLLOW-UP INFORMATION REQUEST.

Attachments

SAM.gov lists 15 files with this notice. Open them on SAM.gov, or ask Claude to read them.

What SAM.gov has posted, oldest first

NoticePostedResponse due
PresolicitationJuly 26, 2026September 10, 2026, 2:00 PM ET
SolicitationSeptember 10, 2026October 15, 2026, 2:00 PM ET
SolicitationOctober 7, 2026October 15, 2026, 2:00 PM ET
SolicitationOctober 12, 2026October 22, 2026, 2:00 PM ET
SolicitationOctober 15, 2026October 22, 2026, 2:00 PM ET
SolicitationOctober 21, 2026October 22, 2026, 2:00 PM ET

Open solicitations like this one

Source: this notice on SAM.gov, from SAM.gov's public extract of contract notices, last loaded November 27, 2026.