Every answer cites notice numbers you can check on SAM.gov. See a real answer

Notices · Solicitation

UT NP ARCH 100(2) Bridges on Delicate Arch Road

Open. Responses are due in 6 days, on December 3, 2026, 4:00 PM ET.

Solicitation number6982AF27B000005
Notice typeSolicitation
AgencyTRANSPORTATION, DEPARTMENT OF, FEDERAL HIGHWAY ADMINISTRATION, 6982AF CENTRAL FEDERAL LANDS DIVISI
Set-asideNone (full and open competition)
NAICS237310 Highway, Street, and Bridge Construction
SBA size standard: $45M average annual receipts
Product or service codeY1LB Construction of Highways, Roads, Streets, Bridges, and Railways
Place of performanceMoab, UT 84532, USA
PostedNovember 24, 2026
Response dueDecember 3, 2026, 4:00 PM ET

Who holds the work now

Largest current award in NAICS 237310 at the Federal Highway Administration, by dollars obligated: FORT MYER CONSTRUCTION CORP, current end date December 31, 2028. It may not be the contract this notice replaces.

Source: USAspending.gov, as of November 3, 2026.

Ask Claude about this notice

Add BidOpps AI to Claude, then type this:

Using BidOpps AI, read 6982AF27B000005 in full and tell me what stage it's at.

Add to Claude

Your first 10 searches are free. No card.

From the attachments

Pulled by AI from 9 of 12 files with text. Check the file before relying on a fact. A point with no row here was not found, which does not mean it doesn't apply. Each quote is the file's own words.

Evaluationlowest price
6982AF27B000005.pdf, page 14: "Accordingly, award of contract, if made, will be made to the lowest responsive, responsible bidder, if funds are available."
Evaluation factorsPrice, with a 10 percent factor added to offers except HUBZone small business concerns that have no…
6982AF27B000005.pdf, page 44: "Offers will be evaluated by adding a factor of 10 percent to the price of all offers, except-"
Questions dueNovember 2, 2026, 4 P.M.
6982AF27B000005.pdf, page 7: "TECHNICAL QUESTIONS REGARDING THIS SOLICITATION WILL NOT BE ACCEPTED AFTER 4 P.M. ON NOVEMBER 2, 2026"
Site visitOctober 8, 2026, optional
6982AF27B000005.pdf, page 9: "Representatives from the Federal Highway Administration (FHWA) will conduct a meeting and site visit on Thursday, October 8, from"
Site visitOctober 8, 2026
QnA 10.15.26.pdf, page 1: "Questions and Answers during Site Visit for the Advertisement of UT NP ARCH 100(2), Bridges on Delicate Arch Road October 8, 2026"
BondingBid guarantee: twenty (20%) percent of the bid price or $3,000,000.00, whichever is less
6982AF27B000005.pdf, page 45: "The amount of the bid guarantee shall be twenty (20%) percent of the bid price"
Contract typefixed-price with economic price adjustment
6982AF27B000005.pdf, page 44: "The Government contemplates award of a FIRM FIXED PRICE with economic price adjustment contract resulting from this solicitation."

The notice text

The text below is SAM.gov's own, unedited.

PROJECT NUMBER: UT NP ARCH 100(2) PROJECT NAME: Bridges on Delicate Arch Road PROJECT DESCRIPTION: Delicate Arch Road (DAR) is within Arches National Park (Park) and provides access to Delicate Arch. DAR is a functional class 1 roadway (Principal Park Road) and is heavily traveled by visitors and often congested during periods with moderate-to-high levels of visitation. DAR crosses three low-gradient ephemeral washes (Salt Valley Wash, Salt Wash, and Winter Camp Wash) near their confluence in the Salt Wash Basin downstream of Wolfe Ranch. Culverts installed during original road construction in the mid-1990s and during subsequent upgrades are inadequate to allow unobstructed stream flow and sediment transport downstream. This existing condition produces flooding and sediment deposition, which creates unsafe conditions for visitors, triggers road closures, potentially strands Park visitors, diminishes visitor experience of the Park, and generates high operational costs associated with traffic management, visitor safety, and cleanup operations. SCOPE OF THE WORK: This project will be designated as Reconstruction (4R) with one segment of restoration (3R), and will design and construct 100’ span concrete bridges at the Salt Valley Wash, Salt Wash, and Winter Camp Wash. The DA roadway profile at each Wash will be raised to accommodate a 10-year design frequency and allow a medium-sized excavator to access each wash. The DA will be realigned at the Salt Valley wash, moving the roadway and new bridge location to the north of the existing roadway and drainage crossing. The remaining 3R sections of the roadway will receive full depth reclamation (FDR) or removal of pavement, including all parking areas, followed by a 4-inch pavement overlay. PRINCIPAL WORK ITEMS: 20420-0000 Embankment Construction: 10,000 CUYD 25101-0300 Placed Riprap, Class 3: 1,725 CUYD 30202-2000 Roadway Aggregate, Method 2: 5,140 TON 40101-5600 Asphalt Concrete Pavement, Gyratory Mix, 1/2-Inch or 3/4-Inch Nominal Maximum Size Aggregate, 0.3 To <3 Million ESAL: 8,300 TON 55201-0200 Structural Concrete, Class A (AE): 752 CUYD 55401-2000 Reinforcing Steel, Epoxy Coated: 138,000 LB 55601-1100 Bridge Railing, Steel, Two Rail: 642 LNFT 56501-0200 Drilled Shaft, 24-Inch Diameter: 750 LNFT 56501-0300 Drilled Shaft, 30-Inch Diameter: 890 LNFT 60901-1300 Curb, Concrete, 15-Inch Depth (Reinforced, Colored): 3,921 LNFT 61701-4500 Guardrail System Mgs, Type 2, Class A Steel Posts: 1,290 LNFT 63506-0500 Temporary Traffic Control, Flagger: 5,800 HOUR ANTICIPATED SCHEDULE: Advertisement – September 2026 Award – November 2026 NTP – December 2026 Contract Completion – December 2028 ESTIMATED COST RANGE: Total estimated cost between $10,000,000 and $20,000,000 This will be solicited as a full and open competition.

Attachments

The files SAM.gov lists with this notice. Open them on SAM.gov, or ask Claude to read them.

What SAM.gov has posted, oldest first

NoticePostedResponse due
SolicitationOctober 5, 2026November 10, 2026, 4:00 PM ET
SolicitationOctober 5, 2026November 10, 2026, 4:00 PM ET
SolicitationOctober 14, 2026November 10, 2026, 4:00 PM ET
SolicitationOctober 21, 2026November 19, 2026, 4:00 PM ET
SolicitationNovember 16, 2026December 1, 2026, 4:00 PM ET
SolicitationNovember 24, 2026December 3, 2026, 4:00 PM ET

Open solicitations like this one

Source: this notice on SAM.gov, from SAM.gov's public extract of contract notices, last loaded November 27, 2026.