Y1DA--NRM-CONST 528-CSI-102 Urology Equipment Site Prep | FY27 NRM

Open. Responses are due in 10 days, on December 7, 2026, 10:00 AM ET.

Solicitation number36C24226B0065
Notice typeSolicitation
AgencyVETERANS AFFAIRS, DEPARTMENT OF, 242-NETWORK CONTRACT OFFICE 02 (36C242)
Set-asideService-Disabled Veteran-Owned Small Business (SDVOSB) Set-Aside (FAR 19.14) (SDVOSBC)
NAICS236220 Commercial and Institutional Building Construction
SBA size standard: $45M average annual receipts
Product or service codeY1DA Construction of Hospitals and Infirmaries
Place of performanceBuffalo, NY 14215, USA
PostedNovember 19, 2026
Response dueDecember 7, 2026, 10:00 AM ET

Who holds the work now

Largest current award in NAICS 236220 at the Department of Veterans Affairs, by dollars obligated: WALSH CONSTRUCTION COMPANY II, LLC, current end date March 25, 2027. It may not be the contract this notice replaces.

Source: USAspending.gov, as of November 3, 2026.

Ask Claude about this notice

Add BidOpps AI to Claude, then type this:

Using BidOpps AI, read 36C24226B0065 in full and tell me what stage it's at.

Add to Claude

Your first 10 searches are free. No card.

From the attachments

Pulled by AI from 8 of 9 files with text. Check the file before relying on a fact. A point with no row here was not found, which does not mean it doesn't apply. Each quote is the file's own words.

Questions dueNovember 30, 2026, 12pm
36C24226B0065_1.docx: "Questions must be received no later than 11-30-2026 12pm"
Site visitsee the quote
36C24226B0065 0003.pdf, page 2: "See attached document: Bid walkthrough attendence form."
Site visitOctober 29, 2026
36C24226B0065 0001.docx: "A pre-bid site visit is scheduled for THURSDAY 10-29-2026 2pm"
Site visitOctober 29, 2026, optional
36C24226B0065_1.docx: "A pre-bid site visit is scheduled for Tuesday 10-29-2026 2pm. Prospective bidders shall meet at MAIN LOBBY, MAIN ENTRANCE NOTE: NO OTHER SITE VISITS WILL BE ALLOWED. INTERESTED BIDDERS ARE STRONGLY ENCOURAGED TO ATTEND."
BondingPerformance and payment bonds
UPDATED-528-19-102-BuffaloUrology Combined Specifications 0…, page 25: "Performance & Payment Bonds: The Performance & Payment Bonds must remain effective throughout the construction period."
Past performanceScheduling consultant: five years as lead project scheduler or previous scheduling experience on at…
UPDATED-528-19-102-BuffaloUrology Combined Specifications 0…, page 93: "The scheduling consultant must have five (5) years of experience as a lead project scheduler or previous scheduling experience on at least three (3) projects of similar size and scope."
Past performancePhotographer: minimum three years in operation with representative portfolio of similar projects
UPDATED-528-19-102-BuffaloUrology Combined Specifications 0…, page 36: "Demonstrable minimum experience of three (3) years in operation providing documentation and advanced indexing/navigation systems"
Past performance15 years construction experience on construction similar to the scope of this Contract
UPDATED-528-19-102-BuffaloUrology Combined Specifications 0…, page 125: "15 years construction experience on construction similar to the scope of this Contract."
Contract typefirm-fixed-price
36C24226B0065_1.docx: "The Government contemplates award Firm Fixed price contract resulting from this solicitation."

The notice text

The text below is SAM.gov's own, unedited.

The purpose of this project is to renovate two Cystoscopy rooms (214 and 215), Procedure Room (212), Procedure Room (211), Check-In area, Office, Control, Vestibule, Dressing, Toilet and Corridor. The two Cystoscopy rooms (214 and 215) will also receive new medical equipment. The Buffalo VAMC requires a Contractor to perform construction work necessary to accomplish this goal. The anticipated Construction Period of Performance is estimated to be 720 days. This effort intends to perform site preparation renovations to support the installation of new medical equipment. The Contractor shall prepare rooms 214 and 215 to receive new equipment. A control room (215-1) is included and an electrical room (214-1) with new electrical panels and equipment is included in the design. In addition, Procedure Rooms 212 and 211, a stretch alcove, a check-in area, office, dressing area and restroom are included in this scope of work

Attachments

The files SAM.gov lists with this notice. Open them on SAM.gov, or ask Claude to read them.

What SAM.gov has posted, oldest first

NoticePostedResponse due
PresolicitationSeptember 15, 2026October 21, 2026, 10:00 AM ET
SolicitationOctober 18, 2026October 21, 2026, 10:00 AM ET
SolicitationOctober 18, 2026December 7, 2026, 10:00 AM ET
SolicitationOctober 19, 2026December 7, 2026, 10:00 AM ET
SolicitationNovember 1, 2026December 7, 2026, 10:00 AM ET
SolicitationNovember 16, 2026December 7, 2026, 10:00 AM ET
SolicitationNovember 17, 2026December 7, 2026, 10:00 AM ET
SolicitationNovember 19, 2026December 7, 2026, 10:00 AM ET