Z1DA--642-22-104 | Upgrade Substation Building 2 Phase 1 for Philadelphia VAMC
Open. Responses are due in 10 days, on December 7, 2026, 4:00 PM ET.
| Solicitation number | 36C24426R0088 |
|---|---|
| Notice type | Solicitation |
| Agency | VETERANS AFFAIRS, DEPARTMENT OF, 244-NETWORK CONTRACT OFFICE 4 (36C244) |
| Set-aside | Service-Disabled Veteran-Owned Small Business (SDVOSB) Set-Aside (FAR 19.14) (SDVOSBC) |
| NAICS | 236220 Commercial and Institutional Building Construction SBA size standard: $45M average annual receipts |
| Product or service code | Z1DA Maintenance of Hospitals and Infirmaries |
| Place of performance | PA 19104, USA |
| Posted | November 19, 2026 |
| Response due | December 7, 2026, 4:00 PM ET |
Who holds the work now
Largest current award in NAICS 236220 at the Department of Veterans Affairs, by dollars obligated: WALSH CONSTRUCTION COMPANY II, LLC, current end date March 25, 2027. It may not be the contract this notice replaces.
Source: USAspending.gov, as of November 3, 2026.
Ask Claude about this notice
Add BidOpps AI to Claude, then type this:
Using BidOpps AI, read 36C24426R0088 in full and tell me what stage it's at.
Your first 10 searches are free. No card.
From the attachments
Pulled by AI from 8 of 38 files with text. Check the file before relying on a fact. A point with no row here was not found, which does not mean it doesn't apply. Each quote is the file's own words.
| Site visit | see the quote Substations Upgrade Building 2-Phase 1_Bid Documents_Specif…, page 7: "Visits to the site by Bidders may be made only by appointment with the Medical Center’s Engineering Officer (COR)." |
|---|---|
| Bonding | performance and payment bonds Substations Upgrade Building 2-Phase 1_Bid Documents_Specif…, page 21: "B. Performance & Payment Bonds: The Performance & Payment Bonds /must remain effective throughout the construction period" |
| Past performance | sample of prior construction projects for scheduling consultant Substations Upgrade Building 2-Phase 1_Bid Documents_Specif…, page 33: "A representative sample of prior construction projects, which the proposed consultant has performed complete project scheduling services." |
| Past performance | 5 years construction experience on similar construction for CQC System Manager Substations Upgrade Building 2-Phase 1_Bid Documents_Specif…, page 98: "5 years construction experience on construction similar to the scope of this Contract." |
| Past performance | Submit evidence that key personnel have successfully performed surface preparation and application… Substations Upgrade Building 2-Phase 1_Bid Documents_Specif…, page 251: "Submit evidence that key personnel have successfully performed surface preparation and application of coating on a minimum of three (3) similar projects within the past three (3) years." |
| Contract type | firm-fixed-price Substations Upgrade Building 2-Phase 1_Bid Documents_Specif…, page 36: "Article, FAR 52.232 – 5 (PAYMENT UNDER FIXED-PRICE CONSTRUCTION CONTRACTS) and VAAR 852.232." |
The notice text
The text below is SAM.gov's own, unedited.
Attachments
The files SAM.gov lists with this notice. Open them on SAM.gov, or ask Claude to read them.
- 2024-12-03_HAZARDOUS AND UNIVERSAL WASTE POLICY.pdf
- 2024-12-03_HAZARDOUS MATERIALS AND WASTE MANAGEMENT PLAN.pdf
- Substations Upgrade Building 2-Phase 1_Bid Documents_Specification_10-21-24.pdf
- ALL-31-SINGLE-LINES-ONE-FILE-012325.pdf
- FMS 138-54 Hot Work Policy.doc
- 36C24426R0088 0002.docx
- Confined Space Entry Program.pdf
- Attachment 3 General Decision Number PA20260003 10012026.docx
- Substations Upgrade Building 2-Phase 1 Combined Drawings.pdf
- Electrical Safety Program.pdf
- 7714_D_2017-04-06 ASBESTOS MANAGEMENT PROGRAM.pdf
- VHA Dir 7714 Asbestos Management Program.pdf
- Fire and Smoke Barrier Pentration Permit.pdf
- Safety Coordination Meeting Safety Policies for SOW Project 642-22-104.pdf
- B6-SUB-PRIMARY-NORMAL-324-371-DWG-FINAL-070623.pdf
- Inspection Final RAC Blank Master.docx
- SAFE PRACTICES FOR WORKING WITH LIVE ELECTRICAL POWER.pdf
- 36C24426R0088 0001.docx
- 36C24426R0088 0004.pdf
- Attachment 2 P09 Final SOW Rev1 Building 2 Substation Phase 1 642-22-104 10202026.docx
- RFI 2 Upgrade Substation 36C24426R0088.docx
- B02-SUB-3.pdf
- FMS SOP 138-44 Fire and Smoke Barrier Penetration Policy.pdf
- B02-SUB-2.pdf
- B6-SITE-POWER-WITH-MANHOLES-DWG-FINAL-070623.pdf
- 2024-12-03_Green Procedure Program.pdf
- FIRE SYSTEM permit 2021 blank.pdf
- MANHOLES 19529-02 VA Hospital of Philedelphia 11.17.22.pdf
- VHA ICRA-1.2 Oct 1 2024.pdf
- B02-SUB-1.pdf
- Blank Above Ceiling Permit.pdf
- Asbestos Control Regulation.pdf
- 36C24426R0088 0003.pdf
- Building 2_LS_SB_G_B FOR REFERENCE ONLY.pdf
- INFECTION PREVENTION AND CONTROL POLICY BEHAVIORAL HEALTH SERVICES.pdf
- Fire Plan.pdf
- S04 Pre-Bid Sign-In Sheet 36C24426R0088 - 642-22-104 - Upgrade Substation.pdf
- 36C24426R0088_1.docx
- Attachment 1 RFI 1 Upgrade Substation 642-22-104.docx
- FMS SOP 138-54 Hot Work Policy.pdf
- Safety and Health During Construction.pdf
- B02-SUB-4.pdf
What SAM.gov has posted, oldest first
| Notice | Posted | Response due |
|---|---|---|
| Solicitation | July 1, 2026 | August 19, 2026, 4:00 PM ET |
| Solicitation | August 3, 2026 | August 31, 2026, 4:00 PM ET |
| Solicitation | August 30, 2026 | August 31, 2026, 4:00 PM ET |
| Solicitation | October 21, 2026 | August 31, 2026, 4:00 PM ET |
| Solicitation | October 21, 2026 | November 20, 2026, 4:00 PM ET |
| Solicitation | October 22, 2026 | November 20, 2026, 4:00 PM ET |
| Solicitation | October 26, 2026 | November 20, 2026, 4:00 PM ET |
| Solicitation | November 19, 2026 | December 7, 2026, 4:00 PM ET |