Every answer cites notice numbers you can check on SAM.gov. See a real answer

Notices · Combined Synopsis/Solicitation

N045--Boiler 3 Oxygen Analyzer and Steam Flow Meter

Closed. Responses were due October 26, 2026, 11:00 AM ET.

Solicitation number36C24727Q0050
Notice typeCombined Synopsis/Solicitation
AgencyVETERANS AFFAIRS, DEPARTMENT OF, 247-NETWORK CONTRACT OFFICE 7 (36C247)
Set-asideService-Disabled Veteran-Owned Small Business (SDVOSB) Set-Aside (FAR 19.14) (SDVOSBC)
NAICS238220 Plumbing, Heating, and Air‑Conditioning Contractors
SBA size standard: $19M average annual receipts
Product or service codeN045 Installation of Equipment: Plumbing, Heating, and Waste Disposal Equipment
Place of performanceDublin, GA 31021, USA
PostedOctober 21, 2026
Response dueOctober 26, 2026, 11:00 AM ET

Who holds the work now

Largest current award in NAICS 238220 at the Department of Veterans Affairs, by dollars obligated: BLUEWAY ONE JV LLC, current end date February 23, 2028. It may not be the contract this notice replaces.

Source: USAspending.gov, as of November 3, 2026.

Ask Claude about this notice

Add BidOpps AI to Claude, then type this:

Using BidOpps AI, read 36C24727Q0050 in full and tell me what stage it's at.

Add to Claude

Your first 10 searches are free. No card.

The notice text

The text below is SAM.gov's own, unedited.

Questions and Answers 36C24727Q0050 Boiler #3 Oxygen Analyzer and Steam Flow Meter RFI Responses Where should the output signals from the new steam flow meter and O2 analyzer terminate? For example, the existing building automation system (BAS), the existing Boiler 3 burner/boiler controls, or a local display only. Burner 3 boiler/burner controls where applicable and local display. Does the government require active O2 trim control to the burner fuel/air ratio, or monitoring and display of the O2 only? Oxygen analyzer must send signals/information to combustion controls to control trim. What is the material of construction for the stack? Is it single or double wall? Stack is double walled. Inside material is steel; outside material is galvanized steel. Stack is 36 D Selkirk Metalbestos Model P.S. Current operating pressure and temperature of the system for boiler #3? Design pressure is 200 psi. Typical operating pressure is 82 psi. Typical operating temperature is about 330 degrees Fahrenheit. What are the available outputs on the physical steam flow meter (e.g., 4-20 mA, Modbus RTU, BACnet MS/TP)? 4-20 mA analog. Is the flow meter wired directly into an analog terminal block on the CB Hawk, or is it wired directly to the facility s Building Automation System (BMS)? Steam flow meter is wired into local CB Hawk analog terminal block. Please provide nameplates for the existing oxygen analyzer and steam flow meter. Oxygen analyzer nameplate: Steam flow meter nameplate:

Attachments

SAM.gov lists 2 files with this notice. Open them on SAM.gov, or ask Claude to read them.

What SAM.gov has posted, oldest first

NoticePostedResponse due
Combined Synopsis/SolicitationOctober 14, 2026October 26, 2026, 11:00 AM ET
Combined Synopsis/SolicitationOctober 21, 2026October 26, 2026, 11:00 AM ET

Open solicitations like this one

Source: this notice on SAM.gov, from SAM.gov's public extract of contract notices, last loaded November 27, 2026.